Welcome to Bhakt Niwas (Phase-two) a premier project by Aakash Developers Pvt. Ltd. Our Fourth project on existing area of Phase One project.
Phase two project was started just after phase one slab casting was done.
In this phase, major trouble was caused by the neighbouring wall which occupied nearly 3 inches area of the on-going construction premises.This was sort after many concerns and consulting the owner of the building stating that the mistake was done by their contractor and we can't make our wall go tilt because of their mistake.
After this the construction work speeded up in 3-4 days. And finally by the end of August the shuttering work began.
Slab was casted by the first week of September 23.
Phase two was an extension to phase one and many of the prehistoric segments were demolished in order to create a modern area with superior look.
11 LakhsINR
Figures-
Projected Cost:
Steel Binding-August 2023
Project Total Cost:
Project Deadline:
Project Start Date:
Project End Date:
No. Of Floors:
No. Of Rooms:
13.4 lakhs INR
3 Month
9 July'23
11 Dec'23
2
3




Disputed area
was resolved later on...
Outer wall Masonry work view 2023


Slab casting phase-two September'23.
After the slab was casted,the demolition work started in the Phase One section. The idea was to create a modern room for the rental purpose for the residents.


Tunneling,excavation work- September 2023
This is Room 2,which consisted of a King sized bedroom,a 5X4 sized kitchen and 3X3 sized store room.
This part took longer than ever,as maximum demolition took place here only.
To be noted,the walls were constructed using bricks and soil instead of mortar!So it was necessary to be plastered using advanced materials having ratio 4:1.


This is Room 2,which consisted of a King sized bedroom,a 5X4 sized kitchen and 3X3 sized store room.
This part took longer than ever,as maximum demolition took place here only.
To be noted,the walls were constructed using bricks and soil instead of mortar!So it was necessary to be plastered using advanced materials having ratio 4:1.
Phase two construction ended up by November 2023 following the aesthetic and paint work


Flooring work- September 2023
Hall Gate fixing work- October 2023




Kitchen finishing work- November 2023
After the Room,which involved the major part of the construction work,Construction of the entry gate to the Hall 2 was started.It had a main window of 2'5''x4' and Gate of 3'15''x6'.
A small portion above bathroom was also created for extra storage.
Following this, the plastering and internal pipeline work was passed from the outer portion of the wall.


Front view of Hall 2- November 2023


view of Hall 2 Finishing work- November 2023
Our Process
Initial Consultation
1
2
Project Planning
3
Construction Phase
We begin with an initial consultation to understand your needs and vision for your dream home in the Lucknow-Kanpur area, ensuring a personalized approach to every project.
Following the consultation, we move into project planning, where we outline timelines, budgets, and design elements, ensuring that every detail aligns with your expectations and our standards.
During the construction phase, our dedicated team works diligently to bring your vision to life, maintaining quality and efficiency while keeping you informed throughout the entire process.
Contact Us
For inquiries about our real estate projects in the Lucknow-Kanpur area, please reach out to Aakash Developers Pvt. Ltd. We look forward to assisting you with your needs.
Contact
Corporate Office:
Block No. 80,Villa No.12,8 Vijay Nagar,Kanpur Metropolitan Region-Kanpur,Uttar Pradesh
Lucknow Office:
Block 2,H.No.720,Sector-H,Near Kursi hwy. ,Jankipuram,Lucknow
(+91)-7376557218
adpl@aakashdevelopers.in
Address
(+91)-7376986837